Updated LinkedIn Microsoft Project Skill Assessment Exam Questions & Answers
Microsoft Project Quiz – Microsoft Project Multiple Choice Questions and Answers
Microsoft Project Multiple Choice Questions and Answers
Microsoft Project questions and answers with explanation for interviews, competitive examination and entrance test. Fully solved examples with detailed answer
Microsoft Project Quiz Topics Covered
All Microsoft Project Topics covered to prepare for all Microsoft Project Examinations or job tests. In the below Microsoft Project Quiz, we have arranged the questions from Create a New Plan, Set Up Resources, Resources To Task, Plan Duration Cost. Track progress, Advance Schedule, and Status Reporting, etc. So, the applicants can verify all the questions and learn the unknown concepts. For free of cost, the most expected questions from Microsoft Project and Answers will be available here for all sort of competitive examinations, University examinations etc.
Note: The most important interview questions asked from Microsoft Projects are given at the end of this Microsoft Project MCQ Mock Test
1. Which of the following is not the default calendar
type?
Night Shift
Standard
24 Hour
Day Shift
2. What is the easiest way to show only the Milestones
and Summary Tasks within your project schedule?
Click on >View,
>Filter, >Milestones
Click on >View, >Group by, >Milestones
Insert the column Milestone, click on the dropdown filter
on the column, then choose “Yes”
Using the AutoFilter, filter for “Duration = 0”
3. Which of the following is NOT a valid view?
Resource Chart
Network diagram
Resource Usage
Task Sheet
4. When you create a resource pool, you cannot easily
see:
A resource hourly cost
Which of the resource’s
tasks are on the critical path
How many projects the resource works on
None of the above
5. What is a variance threshold for cost or other
acceptable variances called?
Acceptable Threshold
Variance Limit
Control Threshold
Cost Limit
6. You can identify project milestones by:
Choosing the appropriate task on the task list and
applying boldface
Indenting the task on the task list
Assigning a duration of
zero-days to the milestone task
Any of the above
7. What are the two ways to filter in Project in MS
Projects?
Custom Filters
Auto Filters
All of above
None of above
8. What are the different types of contour you use in MS
project?
A. Flat
B. Back-loaded
C. Front-loaded
D. All of the above
9. What year was the Macintosh version of Microsoft
projects released?
1998
1991
1996
1986
10. What are the categories of tasks used in MS project?
Summary tasks
Subtasks
Recurring tasks
All of these
11. The Date Format
field can be:
Can be collapsed (and expanded) by clicking the triangle
to the left of the respective summary task name.
The Date Format can be configured to include time.
Both 1 & 2.
Cannot be configured to include time.
12. You would like to add a row at the top of your
project schedule that rolls up or sums all the information below. What is the easiest way to do that?
Insert a Summary Task at the top of your schedule and
indent all tasks below it.
Enable the Project Summary
Task through the Format tab on the Ribbon.
Insert a task at the top of your schedule and establish
the predecessors appropriately.
Enable the Project Summary Task through Project tab and
Project Information.
13. All tasks can be set as recurring.
True
False
14. What is the best option when deciding on a calendar
for your project?
You can create a custom calendar each time you start a
new project
If you create a custom calendar you do not have to
specify a standard, 24-hour, or night calendar
If you specify a custom calendar to use for all projects
it will not recognize resource calendars
None of the above
15. When you open a new project file, the default view
is:
A. Gantt View
B. Network View
C. Resource Graph
D. None of the above
16. How to set work time exception in Project?
Select the project and change the working time
On the calendar choose the day you want to change
Click the exception tab to display it, it will show a
column with the name cell in a blank
row, type a name for the exception and press enter
17. Which of the following is NOT a valid task
constraint?
FNLT - Finish no later than
FBTD - Finish by this date
MSO - Must start on
ALAP - As late as possible
ASAP - As soon as possible
18. The Entry bar:
Is for editing the Task and Resource Name fields only
Performs the same functionality as the Space bar
Is displayed by default
1 & 3
None of the above
19. You would like to see a list of all the resources and
the tasks that they are assigned to. What view best displays this information?
Resource Sheet
Task Usage
Gantt Chart
Resource Usage
20. There are four tasks in your project, and the
duration of your current plan is 22 days. There are FS dependencies between all
four tasks. Task A is four days; Task B is six days; Task C is eight days; and
Task D is four days. Which of the following changes will create a Project plan
with the shortest overall duration?
Create a SF dependency between Task B and Task C.
Create a SF dependency between Task A and Task B.
Create a FF dependency between Task A and Task D
Create a SF dependency
between Task C and Task D.
21. The 'Default
start time' in 'Calendar Options':
Specifies that the time assigned to the Start field when
no time is entered.
Affects the Finish field.
Does not affect the Finish field
1 & 2
1 & 3
22. Working with your project sponsor, you determine that
a few tasks are out of scope for your project.
You would like to somehow adjust your schedule to eliminate those tasks,
but you don’t want to simply delete them just in case they may be needed in the
future. What should you do?
Move the task to after the end date of the project
There is nothing else you can do but delete the task
Remove the Predecessor and Successor from the tasks
Inactivate the tasks
23. True or False? There is an export to Excel feature
for the Task Sheet.
True
False
24. What are the new features available in MS project?
Improved reporting tools
Office 365 Integration
New Project Templates
All the above
25. Where can you set fixed duration, effort driven, and
manually scheduled?
Team Planner
Project Information dialog box
Task form
Resource Sheet
26. How can you recognize the timeframe of a new project?
It can’t be recognized
Choosing options at a backstage
Clicking on the calendar and setting a timeframe
Choosing the project
information in the properties group in the project tab
27. What does WBS stand for?
Work By Schedule
Work Breakdown Structure✔
Work Breakdown Schedule
Work By Software
28. The PMO manager comes to you because she realizes you
have good experience with Microsoft Project 2013. She is wondering if there is an out of the
box view or report that shows Actual Work, Remaining Work and Baseline
Work. Which do you recommend?
Project Overview dashboard
Resource Allocation view
Task Usage view
Work Overview dashboard
29. Clicking on Open Other
Projects displays:
The Office.com templates.
The Backstage Open page
The Import Wizard
The Global.mpp
30. The formula to calculate Cost Variance is:
CV = TV/(AC*TV)
CV = AV + AC
CV = AV/(AC*TV)
CV = EV - AC
31. The Project
Summary Row:Top of Form
Is displayed on row ID = 1
Is displayed on row ID = 0
Is the highest task in your project's Work Breakdown
Structure
1 & 3
2 & 3
32. What are the types of constraint available in MS
project?
As soon as possible
As late as possible
Both A and B
None of these
33. You would like to see graphically that your
milestones have slipped passed the agreed upon Finish dates. What should you add to the milestones?
Finish date
“Must Finish On” constraint
Deadline
“Finish No Later Than” constraint
34. Which of the following is not a constraint type?
Must finish on
As late as possible
Must start on
As quickly as possible
35. You are working on a
project that has tasks with no flexibility. Which constraint type offers no
flexibility?
Must Finish On
Start No Earlier Than
As Soon As Possible
Finish No Earlier Than
36. The ________ new feature in Microsoft Project 2013
allows you to select any task and see the complete chain of predecessors and
successors linked to it.
Task Overview Chart
Task Path Highlighting
PERT Chart
Resource Graph
37. What are the types of constraint available in MS
project?
A. As soon as possible
B. As late as possible
C. Both A and B
D. None of these
38. What does leveling refer to?
Applying duration evenly across resources
Applying work evenly
across resources
None of these
Making all tasks the same duration
39. In a project, duration can
have different units. Which duration unit is not valid?
weeks
hours
days
quarters
40. _______ is the length of time by which a task is ahead of schedule
and will be completed early if continued.
Slack
Lag
Slip
41. Microsoft Project uses
calendars to schedule a project. Which project components can be assigned a
calendar?
tasks and work
work and units
resources and work
tasks and resources
42. What character follows an estimated duration?
?
~
!
*
43. You are working on a
project file that contains many linked subprojects. When saving the files, what
option can you use to immediately save the open files, including those that
have not changed?
Yes to All
Yes
Save As
Save
44. What are the new features available in MS
project?
A. Improved reporting tools
B. Office 365 Integration
C. New Project Templates
D. All the above
45. When you create a task, you can apply subtasks or
sets of subtasks?
To main tasks only but not to subtasks
To any task entered in the
task list entry table
Only to your main task
None of these
46. Which choice is most true about the critical path?
It is determined by Microsoft Project’s automatic
scheduler
It takes in to consideration the slack allowed for
various tasks
It is set as you identify
task dependencies
None of the above
47. What are the two ways to filter in Project?
A. Auto Filters
B. Custom Filters
C. Both of these
D. None these
48. If you want to change the hierarchical structure of a
task or subtask as part of an outline structure for your project, you need to
change the task type or add a deadline date rather than indent or outdent the
task.
TRUE
False
49. What are the new features available in MS project?
Better Presentation Tools
New Project Templates
Task Path
All of the above
50. A resource is assigned to a
task that is scheduled for 2 days. The resource is scheduled for 8 hours (8h)
per day at 100%. The resource performs actual work of 10 hours on the first
day. How has the Peak for this resource changed?
It has changed to 10h.
It has changed to 6h.
It has changed to 125%.
It has changed to 110%.
51. ________ determines how tasks and resources assigned
to these tasks are scheduled.
Schedule
Exception plan
Calendar
Resource pool
52. Notes added to a project file can be viewed _______:
A. When you roll your mouse over the resource or task
with the note
B. When you insert a column called Notes into your task
list entry table
C. If you print all pages of your project
D. All of the above
53. What is SS (start-to-start)) dependency mean?
The work can happen in parallel and the tasks must end at
the same time.
The work can overlap or proceed in parallel.
Task 1 must finish before
Task 2 can start
Task 2 must finish before Task 1 can start
54. Which two of these are easy: Create a pool of resources, delete
resources and add them back in as needed, or share the pool with other
managers?
A. Create a pool of resources and delete them as
necessary
B. Create a pool and share
it with other managers
C. Delete resources as necessary and share resources with
other managers
D. None of the above
55. What is another name for a
work breakdown structure?
a hierarchy of tasks
a linking of tasks
a duration of tasks
a leveling of tasks
56. What are the types of task links in MS project?
Finish to start link
Start to start link
Finish to finish link
All of the above
57. A process that states how formal verification and acceptance of
completed project deliverables will be obtained is documented in the _______.
Procurement Management Plan
Quality Management Plan
Scope Management Plan
Communication Management Plan
58. When adding a resource to a task, to only use them
fifty percent, type this:
Bob[50]
Bob[.50]
Bob(.50)
Bob*.50
59. A report for Earned Value
Over Time has been requested, You decide to use a Microsoft Project visual
report. What values does this report template compare when run?
Earned Value. Planned Value, and Actual
Earned Value and Planned Value
Earned Value and Actual Cost
Planned Value and Actual Cost
60. If you want to sort your resources by last name so
that Brenda Diaz is last on your list and Florian Voss is first on your list,
what sort order should you specify?
Descending
Z-A
Ascending
A-Z
61. What are the categories of tasks used in MS project?
A. Summary tasks
B. Subtasks
C. Recurring tasks
D. All of these
62. You are about to begin a new project. Which of the following Resource Types is NOT
available in Microsoft Project 2013?
Labor
Material
Work
Cost
63. You are preparing a meal
comprising a main dish and multiple side dishes. You want the finish of the
main dish to drive the finish of the side dishes. The main dish will start
before and take longer than the side dishes. You need to create a link from the
main dish to each of the side dishes. Which link type is appropriate?
Start-to-Finish (SF)
Finish-to-Finish(FF)
Finish-to-Start (FS)
Start-to-Start (SS)
65. Out of the following constraints, select the one
which doesn't require start or finish date to be added in order to schedule a
task in MS Project.
A. SNET
B. FNLT
C. ALAP
D. MFO
66. How much should CPI and SPI be in a project ahead of
schedule and costs?
CPI <1; SPI<1
CPI >1, SPI >1
CPI<1 : SPI>1
CPI>1 ;SPI<1
CPI =1; SPI=1
67. What is the smallest denomination of time that can be
assigned when assigning duration to tasks?
Hours
Days
Seconds
Minutes
68. A resource is overallocated
in a project. This resource is responsible for two tasks that are to happen at
the same time. The first of these tasks is on the critical path. Which solution
should you use to remedy the overallocation?
Use the Leveling Gantt view adjust the edays field for
the second task.
Use the Task usage view to change the second task contour
to an early Peak.
Use the Task usage view to change the second task contour
to a bell.
Use the Leveling Gantt view adjust the edays field for
the first task.
69. The _______ is used as a template for other
calendars.
Task calendar
Project calendar
Resource calendar
Base calendar
70. You are in the process of updating your
schedule. You notice that one task has 3
days of Remaining Duration. You speak
with the person assigned to this task and they state that the work is
complete. What should you do?
Mark the task 100% Complete
Enter 0 in Remaining
Duration
Enter a status date for the task
Reschedule uncompleted work
71. One of these is NOT a type of resource?
Schedule
Material
Work
Cost
72. The Team Planner view lets you see:
A. How much money each person will cost on this project
B. What tasks each person
is assigned
C. The schedule for each person on the team
D. None of the above
73. Which of the following is the best way to resolve an
issue in which a resource is overallocated?
Removing that resource from another task
Changing the resource's
availability from 50% to 100%
It cannot be resolved.
Adding another resource to the task
74. Notes added to a project file can be viewed
__________
If you print all pages of your project
When you roll your mouse over the resource or task with
the note
When you insert a column called Notes into your task list
entry table
All of the above
75. SF dependency is ____________?
Task 2 must finish before
Task 1 can start
Task 1 must finish before Task 2 can start
The work can happen in parallel and the tasks must end at
the same time.
The work can overlap or proceed in parallel.
76. You would like to see a list of all the resources and
the tasks that they are assigned to. What view best displays this information?
A. Resource Sheet
B. Task Usage
C. Gantt Chart
D. Resource Usage
77. You would like the ability to edit your typed entries
in the Entry Bar, which appears below the ribbon and above the default Entry
table in the Gantt Chart view. You recently received a new computer and noticed
that the Entry Bar is missing. How do you fix this?
78. Microsoft Project was introduced in the year of
__________
1985
1980
1988
1984
79. Use the Display tab in the Project Options dialog box
to enable the Entry Bar
Change the from Gantt Chart view to Tracking Gantt view.
Use the Advanced tab in the Project Options dialog box to
enable the Entry Bar.
On the View tab on the ribbon, in the Split View group,
select Details.
80. If current data consistently differs from baseline
data, this is an indication that ______.
your actual data must be incorrect.
you must rework your baseline.
your original plan was never accurate.
your original plan is no
longer accurate.
81. How do you mark a task's
progress and have that progress reflected in the task's summary task?
Use the Task tool on the ribbon's Task tab for the
subtask.
Enter a value in the %Complete field.
Use the Task tool on the ribbon's Task tab for the
summary task.
Use the Project Information dialog box.
82. What are the new features available in MS project?
A. New Project Templates
B. Better Presentation Tools
C. Task Pathwrong
D. All of the above
83. You have many tasks in a
project file and want to convert them into milestones. How can you do this?
Recreate the tasks and set them as summary tasks.
Set the tasks as summary tasks.
Unassign any resources from the tasks, as resources are
not needed for milestone task.
Change the tasks' duration to 0.
84. A project has been delayed
by three months. In this project, you have set deadlines that also need to be
delayed by three months. What feature should you use to accomplish both of
these delays?
On the Project tab, click Project Information.
On the Task tab, click Move Task.
On the Report tab, click Compare Projects.
On the Project tab, click Move Project.
85. How many default base calendars
does Microsoft Project set up for a project?
five
three
two
six
86. When two tasks have an FS dependency, but the work
can overlap or be done in parallel, how can you reduce the overall duration of
the project?
Change their dependency to SF
Change their dependency to
FF
Move the deadline forward so that participants work
faster.
Chance their dependency to SS
87. A task has a fixed duration
If the units on the task are changed, what value for the task will
automatically change as a result?
allocation
work
contour
effort
88. You are working with subproject
files (the master project file is not open) and have saved the changes you
made. What happens to the master project when it is opened?
The master project will not reflect any changes until the
subproject files ate opened as well.
The master project will display an error.
The master project will display message stating that
changes were made and the subproject files must be opened first.
The master project will reflect the changes made to the
subproject files.
89. By default, Work is measured in:
Days
Months
Hours
Weeks
90. You just updated the Duration of a task. You notice that the Finish Variance at the
“Level 0” or “Project Summary” row is
now showing 5 days. What does this mean?
The project is on schedule
The project is 5 days
behind schedule
The project is 5 days ahead of schedule
The project needs rebaselined
91. The __________ dialog box allows you select up to
three fields for three levels of sorts within sorts.
sort
project information
group
92. You are working with two
project files. You want the second project to contain some of the same tasks,
along with their work assignments, as the first project. You Choose to copy the
tasks between the projects. What else is copied along with the task when
performing basic copy and paste action?
resources
baseline
calendars
work breakdown structure
93. You are working with a
master project that contains subprojects, and you want to see a list of tasks
on which a subproject file is dependent. How can you do this in Microsoft
Project?
On the Project tab, click Subproject.
On the View tab, click Group by.
On Project tab. click Links Between Projects.
On the View tab, click Filter.
94. You want to manage multiple
projects with one project designated as the master project. Which button on the
ribbon do you use?
Subproject
Share Resources
Move project
Link Between Projects
95. When you create a new blank
project in Microsoft Project, what is the default view?
Resource Sheet
Task Form
Gantt Chart with Timeline
Detail Gantt
96. What is the most accurate way of forecasing EAC and
ETC?
ETC based on New Estimates
ETC based on based on Atypical Variances
Earned Value
ETC based on Typical Variances
97. A project contains numerous linked
tasks. What is the name for a task that is controlled or driven by another
task(s)?
overlapped
predecessor
callout
successor
98. You have several Microsoft Project
files open. One contains sensitive information, so you hide that file. What is
true regarding the hidden file?
The Switch Window lists the hidden file.
The Switch Window command does not list the hidden file.
To unhide the file, select Switch Window.
To view a hidden file, on the View tab, click Arrange
Windows.
99. You are using work
breakdown structure (WBS) codes for an in-progress project. Due to some
schedule changes, tasks have been moved around, which has modified the WBS. How
do you fix the WBS codes?
From the Project tab on the ribbon, click WBS > Define
Code.
From the Project tab on the ribbon, click WBS >
Renumber.
From the View tab on ribbon, click Sort.
From the View tab on the ribbon, in the Data group,
select Group by.
100. When breaking down the
work that needs to be done on a project, what is the smallest unit of work
known as?
work package
duration
work breakdown structure
task assignment
101. The Network Diagram, also known as the ______, shows
dependencies between tasks in a graphical manner.
Resource Graph
Timeline
PERT Chart
Gantt Chart
102. A resource's hours have increased over the span of
five days for a particular task.
The duration has not changed, and the task is effort driven. What element can
you add to the Task Usage view to see what has changed?
Add a column for the actual duration.
Add a column for the level assignments.
Add a column for the Peak value.
Add a column for the assignment.
103. Which of the following is not the default calendar
type?
A. 24 Hour
B. Night Shift
C. Day Shift
D. Standard
104. You are modifying a
project's work breakdown structure (WBS) code. What is the default length for
any selected sequence type?
any
5
3
1
105. You have to deliver a new costume sales website by
September 30 in time for the Halloween season that begins in mid-October. This
is an example of?
Project Scheduling
Project Constraints
Critical Success Factor
Deadline
106. When launching
Project 2013 for the very first time:
You will need to set up the your templates before you can
use it.
You must change the defaults.
You will be presented with the Welcome to Project
tutorial.
The Start screen appears.
107. Setting tasks inactive:
Is the same as cancelling it
Greys them out and formats them with Strike through
A task field named Active is set to 'No' for when a task
it is inactive
All of the above
None of the above
108. Microsoft Projects
Linkedin Test Question Answers
Saving and creating a project is possible:
From and to Microsoft Word
From and To online solutions like SharePoint, Cloud etc.
To and From Excel
None of the above
109. What does CPI of 1.1 mean?
Project schedule overrun by 1.1%
Project is completed ahead
of costs by 10%
Project completed ahead of schedule by 10%
Project cost overrun by 1.1%
110. Which is false
regarding Summary Tasks?
Can be collapsed (and expanded) by clicking the triangle
to the left of the respective summary task name
Can be collapsed (and expanded) by using the Ribbon's
View tab > Outline button (within the Data group)
Are formatted in bold
Outdented relative to their sub-tasks and have an Outline
Level field number greater its sub-tasks
None of the above
111. The Properties
dialog is a place where you should consider populating its fields because:
These fields will be used in tables and automatically
transcribed when running reports
The Comments field allows entering a detailed description
of the project's scope
It could help in document retrieval by searching for
documents based on their properties
All of the Above
112. True or False? When assigning time for projects, you
should also account for non-working time.
True
False
113. The Properties dialog is when setting
the Calculate multiple critical paths option in a master project's Advanced
settings, which statement is correct?
Subprojects will have critical paths calculated
individually.
Individual resources will have critical paths calculated.
Milestones will have critical paths fixed.
Only one critical path will be calculated for a linked
project.
114. What are the types of responsibilities utilized in
MS challenge?
Routine obligations
Subtasks
Precis duties
All of these
115. How can you recognize the timeframe of a new
project?
A. Clicking on the calendar and setting a timeframe
B. It can't be recognized
C. Choosing options at a backstage
D. Choosing the project
information in the properties group in the project tab
116. Out of the following constraints, select the one
which doesn't require start or finish date to be added in order to schedule a
task in MS Project.
SNET
FNLT
ALAP
MFO
117. What are the types of responsibilities utilized in
MS challenge?
A. Precis duties
B. Subtasks
C. Routine obligations
D. All of these
118. You can identify project milestones by _______
Indenting the task
on the task list
Assigning a duration of
zero-days to the milestone task
Choosing the appropriate task on the task list and
applying boldface
Any of the above
119. Creating a template is
possible:
To help standardize Project Option settings
When Save as type is set to Project Template
From a completed project
From an Excel File
All of the above
120. If
you're not certain how Task "Chop the Wood" relates to the work of
"Move the Chairs", which dependency type should you create?
SS
FS
SF
121. The 'Hours per
day' field in the 'Calendar options for the Project':
Is set to 24 hours per day.
By default is 8 Hours and is used when duration is
entered in Days or weeks
No such field exists
Is referred to when Start or Finish is less than 1 day.
122. You click on the resource sheet view and notice that
one of the resource names appears in Red. What does this mean?
The resource is not assigned to any tasks
The resource is
over-allocated
The name is misspelled
The resource has not been properly added to the Resource
Sheet
123. You click on the Resource Sheet view and notice that
one of the resource names appears in Red.
What does this mean?
The name is misspelled
The resource is not assigned to any tasks
The resource is
over-allocated
The resource has not been properly added to the Resource
Sheet
124. True or False? Custom fields created for a resource
can be seen on the task sheet view.
True
False
125. Milestones
are: (select two)
Created by entering a zero (0) in the Work field
Created by entering a zero (0) in the Duration field
Used to mark deadlines
Used to mark the completion of project deliverables
126. You can, using the help of
the Task Inspector to: select all
Identify task drivers, such as predecessors
Identify task that are over budget
Over allocated resources
All of the Above
127. The ________ tab can be used to set working times,
add a holiday to the calendar, and set a baseline.
Calendar
Resource
View
Project
128. The Manually Scheduled
icon in the Task Mode field:
Contains a "?" if the Work and Task Name fields
are left blank
Contains a "?" if the Start or Finish fields
are left blank
When the Duration field contains a "?"
None of the above
129. Microsoft Project allows up to ___
baselines per project.
100
11
2
1
130. The Ribbon, the Quick
Access Toolbar can be modified:
When project plans are closed
When project plans are open
Never
Anytime
131. When you create a resource pool, you cannot easily
see________
Which of the resource’s
tasks are on the critical path
A resource hourly cost
How many projects the resource works on
None of the above
132. What is another name for a summary task?
Hammock task
Overview task
Upper task
High-level task
133. You are in the process of creating a new schedule in
Microsoft Project. You want to ensure
that all tasks added to the schedule will be “Auto Scheduled”. What should you do?
Under Schedule Options,
set New tasks created to “Auto Scheduled”
Under Advanced Options, set New tasks created to “Auto
Scheduled”
Use the Task Mode field
within the Gantt Chart view to change the value to “Auto Scheduled”
Highlight all tasks and use the “Auto Schedule” button
134. You can customize everything in Microsoft
Products as per your convenience at any time.
In regards to calendars:
There only two, Project and Resource calendars
24 Hours, Night Shift and Standard are three (3)
"base" calendars
There are six (6), including the base calendars
135. True or False? Displaying or removing
a group has an effect on the project data.
False
True
136. The Global.mpt is a file
that:
This is a global config file for MSP
This helps drive settings for users
It affects UI of the MSP
All of the above
137.
When you open a new project file, the default view is
Network View
Gantt View
Resource Graph
None of the above
138. You can set both a Constraint and a Dependency for a
given task
True
False
139. The Task Mode:
select two
Affects Duration, Start, and Finish fields
Can be set to Manual- or Auto-Scheduled
Affects Work, Start, and Finish fields
Sets tasks to Fixed Duration
140. The critical path method calculates theoretical
early start and late start and finish dates. Critical path have either
Positive Total Float
Positive or Negative Total
Float
Zero or Negative Total Float
Zero or Negative Total Float
141. Fixed
Duration, Fixed Units and Fixed Work are:Top of Form select two
Are all options of the the Task Type field.
Are all options of the the Task Mode field
Can be all be set as defaults
142. You have a task that spans 5 days in Duration, has
only one Resource assigned, and consists of 40 hours of planned Work. Due to a change in a delivery date, you
discover that you now need to complete this task in 3 days or less. You have an additional resource on the team
who could help with this task. How
should you configure this task before adding the second resource?
Set Type to Fixed Duration, and Effort Driven to Yes
Set Type to Fixed Units, and Effort Driven to Yes
Set Type to Fixed Work, and Effort Driven to No
Set Type to Fixed Work,
and Effort Driven to Yes
143. What is the process of putting tasks in order of the
date they must be completed by?
Nesting
updating
Sequencing
Timing
144. What are the different types of contour you use in
MS project?
Flat
Back-loaded
Front-loaded
All of the above
145. To see all tasks for a person, which view should you
look at?
Task usage
Resource sheet
Task sheet
Resource usage
146. Entering a
start date in the Project Information window:
By default, will cause new
tasks to 'start no earlier than' the start date
Will cause new tasks to commence on the date you entered
as a start date
Will always cause new tasks to start on the current date
None of the above
147. Which two of these are easy: Create a pool of
resources, delete resources and add them back in as needed, or share the pool
with other managers?
Delete resources as necessary and share resources with
other managers
Create a pool and share it
with other managers
Create a pool of resources and delete them as necessary
None of the above
148. The Team Planner view lets you see _______
What tasks each person is
assigned
How much money each person will cost on this project
The schedule for each person on the team
None of the above
149. When setting the Calculate multiple critical paths
option in a master project's advanced settings, which statement is correct?
Subprojects will have
critical paths calculated individually.
Individual resources will have critical paths calculated.
Milestones will have critical paths fixed.
Only one critical path will be calculated for a linked
project.
150. You have a resource on your team who is only
available 50% of the time. She is
responsible for working on only one task next week. The original estimate of Work for this task
was 20 hours. She just informed you that
based upon some new found information, the task is really going to take 30
hours worth of Work to complete. There
is no one else that can assist with this task.
How should you configure this task before updating the Work?
Set Effort Driven to Yes, then input 30 hours Work
Set Type to Fixed Duration, then input 30 hours Work
Set Type to Fixed Units,
then input 30 hours Work
Set Effort Driven to No, then input 30 hours Work
151. How to set a deadline in MS project?
A. Double-click a task -> it will open a task
information dialog box
B. Now, click on the advanced tab
C. Then click on the arrow in the deadline field to show
the calendar and then choose a date
D. All of the above
152. In order to disable the
having the Start Page display when you launch Project 2013:
Uncheck Show the Start screen when this application
starts checkbox in the Option's General page
Uncheck Show the Start screen when this application starts
checkbox from the Ribbon
Uncheck Show the Start screen when this application
starts checkbox from the Quick Access Toolbar
You cannot disable the Start Page
153. To have Task 10 start three days after Task 9
completes, in the predecessor column, type:
T9+3
9FS3
9+3d
All of these
154. Project Standard 2013, and
Project Professional 2013, differ in what way?
Project Standard 2013 permits you to connect to Microsoft
Project Server.
Project Standard costs more.
Project Professional 2013 is for advanced user.
One of them permits you to connect to Microsoft Project
Server 2013.
155. Which choice is most true about the critical path?
A. It takes in to consideration the slack allowed for
various tasks
B It is set as you
identify task dependencies
C. It is determined by Microsoft Project’s automatic
scheduler
D. None of the above
156. Which one of
these is true?
Gantt bar formats differ between Manually versus Auto
Scheduled tasks
Summary tasks may also be set to Manually Scheduled or
Auto Scheduled
Project Summary tasks are Auto Scheduled
All of the above
157. What
is CPI=?
Earned Value /Actual Schedule
EV/AC
Actual Schedule/EV
Actual Cost/Earned Value
158. Where can you set fixed
duration, effort driven, and manually scheduled?
Team Planner
Project Information dialog box
task form
Resource Sheet
159. You want to switch the
scheduling mode for a project from scheduling from a start date to scheduling
from a finish date. This action will change the default constraint from As Soon
As Possible to As Late As Possible. Which dialog box should you use to make
this change?
Resource Information
Project Information
Task Information
Change Working Time
160. Which of the following is NOT a valid task
constraint?
FNLT - Finish no later than
FBTD - Finish by this date
MSO - Must start on
ALAP - As late as possible
ASAP - As soon as possible
161. Your Resource List automatically notifies you:
A. Which people earn the least money, thus decreasing
project costs
B. When someone is
scheduled for a task on his day off
C. Whether someone works full or part time
D. None of the above
162. A project contains many
elements. What is used to describe the sum of the work required?
task links
Resource Sheet
work breakdown structure
baseline
163. When you create a task, you can apply subtasks or
sets of subtasks:
A. Only to your main task
B. To any task entered in
the task list entry table
C. To main tasks only but not to subtasks
D. None of the above
164. You are in the process of updating your schedule.
You notice that one task has 3 days of Remaining Duration. You speak with the
person assigned to this task and they state that the work is complete. What
should you do?
A. Mark the task 100% Complete
B. Enter 0 in Remaining
Duration
C. Enter a status date for the task
D. Reschedule uncompleted work
165. Your Resource List automatically notifies
you________
When someone is scheduled
for a task on his day off
Which people earn the least money, thus decreasing
project costs
Whether someone works full or part time
None of the above
166. Which option is not
available in the Report tab on the ribbon?
New Report
Network Diagram
Recent
Custom
167. The default task type in Microsoft Project is ____.
fixed work
fixed units
fixed duration
fixed start
168. You are troubleshooting a schedule
on someone else's computer The schedule has 10,000 tasks. When a change is made
to a task's duration on a Fixed Units task, the start and finish dates do not
change. change highlighting does not appear, and the Gantt Chart bat does not
update. What is the cause of this issue?
Inserted projects are calculated like summary tasks is
selected.
Calculate multiple critical paths is not selected.
One of the Com add-ins is not selected.
Calculate project after each edit is set to Off.
169. To see how changes to one task affect the rest of
the project and to track schedule
changes _____.
Resource Leveling
Task Inspector
Gantt Chart
Task Path Highlighting
170. You would like to understand which
tasks are critical and which are not. When looking at the Gantt chart, how are
these tasks identified by default?
Critical tasks are indicated in red and other tasks are
indicated in blue.
Critical tasks are indicated in dark blue end other tasks
are indicated in light blue.
Critical tasks are indicated in a report while the Gantt
chart indicates all tasks in blue.
Critical tasks are indicated with an icon and other tasks
are indicated in blue.
171. You can set both a Constraint and a Dependency for a
given task:
True
False
172. How to set a deadline in MS project?
Double-click a task -> it will open a task information
dialog box
Now, click on the advanced tab
Then click on the arrow in the deadline field to show the
calendar and then choose a date
All of the above
173. To see individual resource details by task, which
view should you look at?
Task usage
Resource usage
Task sheet
Resource sheet
174. You just updated your schedule. You need a graphical view that shows how your
current schedule compares to the Baseline.
Which view should you use?
Detail Gantt view
Tracking Gantt view
Leveling Gantt view
Gantt Chart view
175. A calendar can be associated with a:
Task
Resource and Project
Project
Resource
All of these
176. Which of the following is
a best practice when estimating the project timeline? Select all that apply.
Prove competency by trying to resolve timeline concerns
without input.
Work quickly through the planning process to get the
project started
Escalate any timeline concerns to stakeholders
Be thorough during the planning process
177. After "Pour the Foundation" and
"Build the Frame" are both finished, "Mount the Drywall"
should start immediately. To put these task relationships in your plan, which
dependency types should you create?
"Pour the
Foundation" Finish-to-Finish with "Build the Frame," and
"Mount the Drywall" Finish-to-Start with "Pour the
Foundation."
"Pour the Foundation" Start-to-Start with
"Build the Frame," and "Mount the Drywall" Finish-to-Start
with "Pour the Foundation."
"Pour the Foundation" Finish-to-Start with
"Build the Frame," and "Build the Frame" Finish-to-Start
with "Mount the Drywall"
178. What is a strategy to overcome the
planning fallacy?
Add task buffers
Add additional teammates
Expand the project scope
Increase the budget
179. When creating a critical
path, what does a network diagram help visualize? Select all that apply.
The tasks that can be performed in parallel
Which non-essential tasks are not on the critical path
The path of work from the start to the end of the
project
Which skilled teammate can work on each task
180. Fill in the blank: A
Kanban board utilizes cards placed in columns to _________
estimate the budget
set the timeline
organize documents
manage tasks
181. In manual scheduling, changes to which of the
following updates task dates?
Project calendars
Constraints
Task dependencies
None of the above
182. Gantt charts give project
teams a visual representation of project tasks. What else do Gantt charts
include?
Roles and responsibilities
Resources deliverables, and success metrics
Stakeholder contact information and budget items
Due dates, durations, and milestones
183. ______ is an overlap between two tasks that are
linked by a dependency.
Lag time
Slip
Lead time
Delayed start time
184. You want to switch the scheduling mode for a project
from scheduling from a start date to scheduling from a finish date. This action
will change the default constraint from As Soon As Possible to As Late As
Possible. Which dialog box should you use to make this change?
Resource Information
Project Information
Task Information
Change Working Time
185. What is the best option when deciding on a calendar
for your project?
If you create a custom calendar you do not have to
specify a standard, 24-hour, or night calendar
If you specify a custom calendar to use for all projects
it will not recognize resource calendars
You can create a custom
calendar each time you start a new project
None of the above
186. You click on the resource sheet view and notice that
one of the resource names appears in Red. What does this mean?
A. The name is misspelled
B. The resource is not assigned to any tasks
C. The resource is
over-allocated
D. The resource has not been properly added to the
Resource Sheet
187. What tool can a project
manager use for organizing all aspects of a complex project?
Roles and responsibilities
Resources, deliverables, and success metrics
Work management software
A digital document
188. Which project management
tool uses cards to track and visualize task progress?
Kanban board
digital document
Gantt chart
spreadsheet
189. You are managing a
construction project schedule with key tasks that have dependencies on each
other. You need to supply key materials to your team they begin to build
different of the building. All materials must be inventoried before they can be
used for the project. The completion of the materials delivery and inventory
task, which will take longer than the different building sections, will drive
the completion of the building sections. You need to create a link from the
delivery and inventory task to of building task. Which link type is
appropriate?
Finish-to-Finish (FF)
Start-to-Start (SS)
Start-to-Finish (SF)
Finish-to-Start (FS)
190. Which of the following is NOT true of deadline
dates?
Deadline dates can affect the total slack on tasks.
Deadline dates indicate a target date you don't want to
miss.
Deadline dates affect task
scheduling.
Deadline dates can be set on summary tasks and individual
tasks.
191. You are working on a
project schedule. You need two tasks to end at the same time so that your
review team can do their work on both tasks. Which link type is appropriate?
Start-to-Start (SS)
Finish-to-Start (FS)
Start-to-Finish (SF)
Finish-to-Finish (FF)
192. If a task is ______, as resources are added or removed
on the assignment, the work remains constant and is redistributed among the
resources.
ahead of schedule
effort-driven
work-driven
behind schedule
193. You want to change the
view of the timescale on Gantt chart to be more granular. How many tiers does
the timescale support?
three
five
ten
four
194. When assigning a time duration to a task, what is
the abbreviation for "months"?
mths
mos
mo
m
195. A project currently has a
software developer performing two tasks at the same time. The first task is 5
days long; the second task is day long. It has been decided that the developer
can take some time to work on the shorter task in the middle the longer task
without impacting the schedule. What is the best way to this?
Create a link between the tasks with dependency.
Change the first task's contour to Double Peak.
Add lag time of -1d to the second task.
Split the longer task to accommodate the shorter task.
196. In a fixed unit task, if you revise Duration, what
happens?
Timeline is recalculated.
Dependencies are reassigned
Work is recalculated.
Units are recalculated.
197. When you begin a new project, you can identify its
timeframe by:
A. Clicking on the Calendar and setting Timeframe
B. Going back stage and choosing options
C. Going to the Project tab
and in the Properties group choose Project Information
D. None of the above
198. A graduated scale of rates
can be created for a resource by using cost rate tables. What is the maximum
number of cost rate tables each resource in a project have?
five
ten
six
two
199. On the Task tab, the _____ group provides buttons to
mark the percent complete, link tasks to one another, and inactivate a task.
Task
Data
Properties
Schedule
200. On your computer,
Automatically add new views, tables, filters, and groups to the global is
selected. You are using a custom filter that you created in one of your
schedules, and you modify it to better meet your needs. You now notice that
this modification is not available in other schedules. How do you fix this?
Using More Filters, make a copy of the modified filter.
In the Project Options dialog bays clear and reselect automatically
add new views, tables, filters and groups to the global.
Using the Organizer, copy the modified filter from your
schedule to global .mpt and replace the filter when prompted.
Using Compare Projects, select the appropriate options
from the Task Table and Resource Table lists.
201. Which of the following is NOT a risk-diagramming
technique?
System Flowcharts
Control Diagram
Influence Diagrams
Cause and Effect Diagrams
202. You need to modify a resource pool. When opening the
file that contains the pool, which option is not valid?
Open as read-write into d new master project file.
Open as read-write and allow others to use the pool.
Open as read-only and allow others to use the pool.
Open as read-write while locking others from updating the
pool.
203. Custom fields created for a task can be seen on the
resource sheet view. True or False?
True
False
204. Which of the following is NOT a valid task
constraint?
FNLT - Finish no later than
FBTD - Finish by this date
MSO - Must start on
ALAP - As late as possible
ASAP - As soon as possible
205. You are the project manager on the rehab of an
apartment building. Before you can get the Certificate of Occupancy, which is
necessary to complete the project, the wiring must be installed. What type of
precedence relationship is this?
Finish to Finish
Start to Finish
Start to Start
Finish to Start
206. When you create a task, you can apply subtasks or
sets of subtasks?
A. Only to your main task
B. To any task entered in
the task list entry table
C. To main tasks only but not to subtasks
D. None of these
207. Project lets you customize the calendar for
__________
The people working on the project
The materials used on the project
The project duration
The tasks scheduled for
the project
208. There are four tasks in your project, and the
duration of your current plan is 22 days. There are FS dependencies between all
four tasks. Task A is four days; Task B is six days; Task C is eight days; and
Task D is four days. Which of the following changes will create a Project plan
with the shortest overall duration?
Create a SF dependency between Task A and Task B.
Create a FF dependency between Task A and Task D
Create a SF dependency between Task C and Task D
Create a SF dependency between Task B and Task C.
209. Which of the resources affect task scheduling?
Work and Cost
Work
Material
Work and material
210. When you create a task, you can apply subtasks or
sets of subtasks?
To any task entered in the
task list entry table
To main tasks only but not to subtasks
Only to your main task
None of the above
211. You were just asked to take over a project. The previous project manager had developed a
schedule in Microsoft Excel. It has 262
tasks, each with Duration in days and Resource Names assigned. You prefer to manage your projects using
Microsoft Project. What’s the best way
to get the information out of Excel and into Microsoft Project?
Use the Gantt Chart Wizard
Select all the information in Excel, Copy and Paste
directly into Microsoft Project
Open the Excel file
directly from within Microsoft Project, which will convert and map Tasks,
Durations, and Resources assigned into Project fields
Create a VBA macro
212. Which of the following defines the project scope in
terms of deliverables and components, and provides the framework on which the
project status is based?
Work package
Work breakdown structure
Baseline
Milestone
213. When you begin a new project, you can identify its
timeframe by?
Going to the Project tab
and in the Properties group choose Project Information
Going back stage and choosing options
Clicking on the Calendar and setting Timeframe
None of the above
214. You are in the process of updating your schedule.
You notice that one task has 3 days of Remaining Duration. You speak with the
person assigned to this task and they state that the work is complete.
Enter a status date for the task
Enter 0 in Remaining
Duration
Mark the task 100% Complete
Reschedule uncompleted work
215. How to set work time exception in Project?
A. Select the project and change the working time
B. On the calendar choose the day you want to change
C. Click the exception tab to display it, it will show a
column with the name cell in a blank row, type a name for the exception and
press enter
D. All of these
The most important interview questions asked from Microsoft Projects
What is the project schedule?
Schedules provide an overview of the project’s milestones, tasks, and dependencies. Tracking a project's progress can be done with it.
Where can you see the project information?
An overview of all your project's tasks is displayed in the Project view. The table at the top of the view shows summary information for the entire project, and you can expand each row to see more detailed information. You can manage your Projects in Project Manager.
How would you define an appropriate task?
The goal of a project can be achieved by completing an individual task within a project plan. Tasks are specific units of work that must be completed to reach the goal. Whenever possible, tasks can be broken down into smaller steps, but they should always be manageable and achievable within the project's timeline. Planning, researching, executing, and monitoring/evaluation are some of the most appropriate tasks for various types of projects.
What is a summary task?
You can use summary tasks to group related tasks together, as well as containers for tasks with subtasks in your project plan. Summary tasks can be dependent on other summary tasks, and they can be assigned start and end dates. You can also add text to summarize the contents of a summary task.